A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter:
✑ Project title description
✑ Preassigned resources
✑ Budget
✑ WBS
✑ Measurable project objectives
Which of the following components should be a part of the project management plan instead of the project charter?

Answer options

Correct answer: D

Explanation

The Work Breakdown Structure (WBS) is a detailed breakdown of the project deliverables and should be part of the project management plan, as it guides project execution and monitoring. The other options, such as project title, preassigned resources, budget, and measurable objectives, are typically included in the project charter to outline the project's scope and goals.