CompTIA Project+ (PK0-004) — Question 171
Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project's current status.
Which of the following types of reports should the project sponsor use to quickly summarize the status report data?
Answer options
- A. Pie chart
- B. Run chart
- C. Project schedule
- D. Dashboard information
Correct answer: D
Explanation
The correct answer is D, as dashboard information presents a concise and clear visual representation of key metrics, making it ideal for summarizing project status quickly. In contrast, a pie chart (A) and run chart (B) focus on specific data points rather than an overall summary, while a project schedule (C) provides detailed timelines instead of a high-level overview.