CompTIA Project+ (PK0-004) — Question 13

A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days.
Which of the following characteristics classifies this as a project?

Answer options

Correct answer: C

Explanation

The correct answer is C, Iterative, because the product development has a specified start and end date, making it a project with defined phases. Options A and B are incorrect since they imply ongoing or repetitive processes rather than a specific timeframe. D, Temporary, is also not correct as it does not reflect the iterative nature of the project within the given deadline.