CompTIA Project+ (PK0-004) — Question 129
The stakeholders who are available for the user acceptance test do not understand the project's requirements. The tester is trying to identify who requested the feature, but there is no information available. Which of the following components is missing?
Answer options
- A. RTM
- B. Quality plan
- C. Project schedule
- D. SOW
Correct answer: A
Explanation
The correct answer is A, RTM (Requirements Traceability Matrix), which helps track the requirements and their origins. Without the RTM, it's difficult to identify who requested specific features. The other options, while relevant to project management, do not specifically address the traceability of requirements to stakeholders.