CompTIA Project+ (PK0-004) — Question 120

A milestone task on the critical path has been completed.
Which of the following should the project manager notify?

Answer options

Correct answer: C

Explanation

Notifying the Project sponsor is crucial as they are typically responsible for the overall success of the project and need to be kept informed of significant progress like milestone completion. The other options, while important, do not hold the same level of responsibility for project oversight as the sponsor does.