CompTIA Project+ (PK0-004) — Question 101

Which of the following job roles is primarily tasked with communicating the project timeline changes?

Answer options

Correct answer: B

Explanation

The Project manager is the individual accountable for overseeing the project and ensuring that all stakeholders are informed of any changes, including those related to the timeline. While the Project scheduler focuses on the scheduling aspect, and the Project coordinator assists in various project tasks, it is ultimately the Project manager who communicates significant updates to the project timeline.