CompTIA Project+ (PK0-004) — Question 100
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?
Answer options
- A. December 18
- B. December 19
- C. December 20
- D. December 21
- E. December 22
Correct answer: A
Explanation
Task A runs from December 15 to December 16. Task C starts immediately after Task A, on December 17, and lasts for three days, finishing on December 19. Task D starts after Task C, which means it begins on December 20. Therefore, the anticipated start date for Task D is December 20, making option A incorrect as it does not reflect the correct timeline.