CompTIA A+ Core 2 (220-1102) — Question 602

An administrator's change was approved by the change management review board. Which of the following should the administrator do next?

Answer options

Correct answer: C

Explanation

The correct action for the administrator after approval is to implement the change, as this is the next logical step in the change management process. Performing a risk analysis, assigning a change coordinator, and verifying testing results are important but occur either before or during the implementation phase, not immediately after approval.