CompTIA A+ Core 2 (220-1002) — Question 146
A technician is scheduled to upgrade a grocery store's network equipment at 11:00 p.m. There are only a few shoppers in the store; therefore, the store manager wants the technician to start the upgrade early. Which of the following is the NEXT step the technician should perform?
Answer options
- A. Create a back-out plan for the store
- B. Review the change request document
- C. Draft the new network diagrams
- D. Get approval from the Change Advisory Board
Correct answer: D
Explanation
The technician must first obtain approval from the Change Advisory Board before making any changes to the network. This ensures that all stakeholders are aware and agree with the modification. The other options, while important, should follow after securing the necessary approval.