Implementing and Operating Cisco Data Center Core Technologies (DCCOR) — Question 172
An engineer must implement the FCoE on the Cisco Nexus 9000 Series Switch-based infrastructure. The deployment will contain dual-homed fabric extenders and must support jumbo frames with port channels. Which two sets of actions complete the configuration? (Choose two.)
Answer options
- A. Create a virtual Fibre Channel Interface. Bind vFC to physical interface.
- B. Configure the interface with mtu 9516. Disable the feature NPIV.
- C. Create a dedicated VSAN for FEX. Bind VSAN to FEX uplinks.
- D. Execute fcoe enable-fex. Configure FEX uplinks with mtu 9216.
- E. Create a FCoE switch profile. Enable config sync.
Correct answer: A, D
Explanation
Option A is correct because creating a virtual Fibre Channel Interface and binding it to a physical interface is essential for FCoE configuration. Option D is also correct as executing fcoe enable-fex and configuring FEX uplinks with mtu 9216 is necessary to support jumbo frames. Options B, C, and E are not required steps for this specific configuration.