Implementing and Operating Cisco Data Center Core Technologies (DCCOR) — Question 172

An engineer must implement the FCoE on the Cisco Nexus 9000 Series Switch-based infrastructure. The deployment will contain dual-homed fabric extenders and must support jumbo frames with port channels. Which two sets of actions complete the configuration? (Choose two.)

Answer options

Correct answer: A, D

Explanation

Option A is correct because creating a virtual Fibre Channel Interface and binding it to a physical interface is essential for FCoE configuration. Option D is also correct as executing fcoe enable-fex and configuring FEX uplinks with mtu 9216 is necessary to support jumbo frames. Options B, C, and E are not required steps for this specific configuration.