APICS Certified Supply Chain Professional (CSCP) — Question 414
Early supplier involvement (ESI) in product design and development is most likely to result in:
Answer options
- A. design suggestions and reduced cycle time.
- B. distribution strategy suggestions and reduced lead times.
- C. distribution strategy suggestions and product price suggestions.
- D. product price suggestions and design suggestions.
Correct answer: A
Explanation
The correct answer, A, highlights that involving suppliers early can enhance design inputs and streamline the development process, thus reducing the cycle time. Options B, C, and D focus on distribution and pricing strategies, which are not the primary benefits of early supplier involvement in design.