APICS Certified Supply Chain Professional (CSCP) — Question 16
Which of the following types of lead times is related most closely to a supplier performance measure?
Answer options
- A. Fulfillment
- B. Replenishment
- C. Overall
- D. Process
Correct answer: B
Explanation
Replenishment lead time is specifically linked to how quickly a supplier can provide new stock when needed, making it a critical measure of supplier performance. Fulfillment, overall, and process lead times do not focus specifically on supplier efficiency and effectiveness in delivering goods.