VMware Horizon 8 Specialist — Question 51
An administrator has been tasked with configuring vRealize Operations to ensure that workload performance across the VMware SDDC is the main priority. In the event of an issue, remediation activities should be automatically completed to minimize any impact to running workloads. A maximum of 10% cluster resources should be reserved for burst capacity.
Which option should the administrator configure to meet these requirements?
Answer options
- A. Business Intent
- B. Reclamation
- C. Operational Intent
- D. Rightsizing
Correct answer: A
Explanation
The correct answer is A, Business Intent, as it focuses on aligning resources with performance objectives and automating remediation to ensure workloads are prioritized effectively. Options B (Reclamation) and D (Rightsizing) deal with resource optimization and efficiency rather than automatic remediation in response to issues. Option C (Operational Intent) is more about managing operations rather than directly aligning with workload performance priorities.