VMware Horizon 8 Specialist — Question 15
An administrator is using vRealize Operations for capacity modeling to determine how many more ESXi servers are needed to increase time remaining and capacity remaining score.
What can be used to accomplish this goal?
Answer options
- A. What-If Analysis
- B. Rightsizing
- C. Operations Overview
- D. Workload Optimization
Correct answer: A
Explanation
The correct answer is A, What-If Analysis, as it allows administrators to simulate changes in their environment and predict the impact on capacity. The other options, such as Rightsizing, Operations Overview, and Workload Optimization, focus on different aspects of resource management but do not specifically address capacity modeling for future server needs.