VMware Cloud Director Specialist (2022) — Question 47
During the design phase for a greenfield VMware Cloud Foundation (VCF) deployment, the following design decisions have been agreed upon:
Stretched Cluster needs to be deployed
Identity and Access Management for VMware Cloud Foundation needs to be deployed
The Infrastructure Architect is working with the client to fill the Planning and Preparation Workbook. The Option for Stretched Cluster has been set to 'Include'. The 'Identity and Access Management' is displaying an error, and its Final Result is stating 'Excluded'.
Which option should be enabled in the Planning and Preparation Workbook to address the issue?
Answer options
- A. Apply Signed Certificates
- B. Consolidated Management Domain
- C. Clustered Workspace One Access
- D. NSX Routing for Management Domain
Correct answer: D
Explanation
Enabling NSX Routing for the Management Domain is necessary to facilitate proper communication and functionality for Identity and Access Management in a Stretched Cluster setup. The other options do not directly address the requirements for Identity and Access Management or the specific needs of a Stretched Cluster deployment.