VMware Cloud Director Specialist (2022) — Question 125
What is the correct sequence of steps to add a new VI Workload Domain in a VMware Cloud Foundation environment?
Answer options
- A. 1. Configure DNS. 2. Create a network pool. 3. Commission hosts. 4. Add licenses to SDDC Manager. 5. Create the workload domain.
- B. 1. Configure DNS. 2. Commission hosts. 3. Create a network pool. 4. Add licenses to SDDC Manager. 5. Create the workload domain.
- C. 1. Create a network pool. 2. Commission hosts. 3. Add licenses to SDDC Manager. 4. Create the workload domain.
- D. 1. Create a network pool. 2. Commission hosts. 3. Create the workload domain. 4. Add licenses to SDDC Manager.
Correct answer: A
Explanation
The correct answer is A because it follows the required sequence of configuring DNS first, then creating a network pool, commissioning hosts, adding licenses to SDDC Manager, and finally creating the workload domain. The other options either misplace the order of critical steps or omit necessary actions, which would hinder the successful addition of a new VI Workload Domain.