VMware NSX-T Advanced Deployment (VCAP-NV Deploy) — Question 44
An organization has onboarded a new business unit whose role is to test the applications 5 days prior to the release date. The Service Broker administrator should allow a 2- day extension for these deployments before they are deleted permanently.
Which two options must be configured in the lease policy to meet the requirements? (Choose two.)
Answer options
- A. A maximum lease of 5 days
- B. A maximum lease of 7 days
- C. A total maximum lease of 7 days
- D. A total maximum lease of 5 days
- E. A grace period of 5 days
Correct answer: B, C
Explanation
The correct answers are B and C because the total duration for testing and the extension needs to be at least 7 days. Option A only allows for 5 days, which does not accommodate the testing period plus the extension, while option D also falls short by setting a total maximum lease of 5 days, failing to meet the extended requirement.