VMware vSphere 8.x Advanced Design (VCAP-DCV Design) — Question 52

An architect is working with stakeholders to define requirements for architecting a new VMware vSphere design.
What are two strategies for engaging with stakeholders to achieve this goal? (Choose two.)

Answer options

Correct answer: C, D

Explanation

Options C and D are correct because they involve direct engagement with stakeholders to gather comprehensive business and technical requirements, which is crucial for effective architecture design. Option A is too narrow as it focuses solely on the technical team, while option B limits engagement to a specific group rather than including all relevant stakeholders. Option E focuses only on business requirements, missing the technical aspect needed for a complete architecture.