VMware vRealize Operations Manager — Question 30

A vRealize Automation Tenant Administrator has identified a virtual machine with low resource utilization. The owner has been given 5 days to respond to the reclamation request. The blueprint used to build the virtual machine has an archive period of 10 days and there are 21 days left in the original machine lease.
If the owner responds today confirming the virtual machine is no longer needed, how many days will elapse before the virtual machine is destroyed?

Answer options

Correct answer: A

Explanation

The correct answer is 10 days because once the owner confirms the virtual machine is no longer needed, it will enter the archive period defined by the blueprint, which is 10 days. The lease time of 21 days is irrelevant in this case, as the destruction is contingent on the archive period. The other options do not reflect the correct timeline for destruction.