VMware vSphere 6.5 Professional (2017) — Question 3
What are two requirements to enable EVC in vSphere DRS cluster? (Choose two.)
Answer options
- A. CPUs must be from the same vendor.
- B. EVC must use the lowest possible baseline supported by the hardware.
- C. CPUs must be in the same family and of the same speed.
- D. No VMs may be running in the cluster.
Correct answer: A, B
Explanation
The correct answers are A and B because EVC requires that all CPUs come from the same vendor to ensure compatibility and that it uses the lowest baseline to maximize hardware support. Options C and D are incorrect; while CPU family and speed can affect performance, they are not strict requirements for enabling EVC, and having VMs running does not inherently prevent EVC activation.