An administrator configures a lease policy with the following settings:
✑ Maximum lease (days): 10
✑ Maximum total lease (days): 30
✑ Grace period (days): 5
If a user does not respond to any emails, after how many days will the deployment be destroyed?
Answer options
- A. 35
- B. 15
- C. 40
- D. 10
Correct answer: A
Explanation
The deployment will be destroyed after 35 days, which is the sum of the maximum total lease of 30 days and the 5-day grace period. The other options do not consider both the maximum total lease and the grace period, leading to incorrect calculations.