VMware Aria Automation 8.x Professional — Question 7

What are the two pre-requisites for the VMware Aria Automation onboarding plan to run successfully? (Choose two.)

Answer options

Correct answer: B, E

Explanation

The correct answers, B and E, are vital for the onboarding process. B ensures that there is a project with user access to cloud zones, which is necessary for resource allocation, while E confirms that the cloud account and zones are correctly set up for the machines. Options A, C, and D are not prerequisites for the onboarding plan to function effectively.