VMware Aria Automation 8.x Professional — Question 21
An administrator configures a lease policy with the following settings:
Maximum lease (days): 10 -
Maximum total lease (days): 30 -
Grace period (days): 5 -
If a user does not respond to any emails, after how many days will the deployment be destroyed?
Answer options
- A. 10
- B. 15
- C. 35
- D. 40
Correct answer: B
Explanation
The deployment will be destroyed after 15 days. This is calculated by adding the maximum lease period of 10 days to the 5-day grace period, resulting in a total of 15 days. The other options do not account for the grace period correctly or exceed the maximum total lease days.