VMware Aria Automation 8.x Professional — Question 21

An administrator configures a lease policy with the following settings:

Maximum lease (days): 10 -

Maximum total lease (days): 30 -

Grace period (days): 5 -
If a user does not respond to any emails, after how many days will the deployment be destroyed?

Answer options

Correct answer: B

Explanation

The deployment will be destroyed after 15 days. This is calculated by adding the maximum lease period of 10 days to the 5-day grace period, resulting in a total of 15 days. The other options do not account for the grace period correctly or exceed the maximum total lease days.