VMware vSAN Administrator (2025) — Question 8

An architect has made an assumption that existing support staff are adequately skilled to operate the proposed infrastructure design.
The risk associated with this assumption would be that existing support staff are inadequately skilled to operate the proposed infrastructure design.
How would the architect mitigate the risk?

Answer options

Correct answer: B

Explanation

The correct answer is B, as training existing staff ensures they are equipped with the necessary skills to manage the new infrastructure. A skills assessment alone (A) does not provide a solution, while engaging a third-party company (C) does not develop in-house capabilities. Hiring additional staff (D) increases capacity but does not address the skill gaps of the existing team.