VMware vSAN Administrator (2025) — Question 27
An organization is evacuating their current datacenter and moving all workloads to a new datacenter. The organization has a total of 800 workloads to move, and the migration must be completed with no downtime within a planned change window that is scheduled to occur in four weeks.
What migration method will meet the requirements?
Answer options
- A. HCX Replication Assisted vMotion
- B. Cross vCenter vMotion
- C. HCX OS Assisted Migration
- D. HCX Bulk Migration
Correct answer: A
Explanation
HCX Replication Assisted vMotion is the best method to migrate workloads without downtime, as it allows for ongoing replication and minimizes service interruption. Cross vCenter vMotion typically requires a short downtime, while HCX OS Assisted Migration and HCX Bulk Migration may not be suitable for such a large number of workloads within the given timeframe.