VMware vSAN 8.x Administrator — Question 34
During a transformation project kick-off meeting, an architect highlights specific areas on which to focus while developing the new conceptual design.
Which statement is the business requirement?
Answer options
- A. Sites must support a network latency of less than 12 ms RTT.
- B. There is no budget specifically assigned for disaster recovery.
- C. The solution must continue to operate even in case of an entire datacenter failure.
- D. The project should use the existing storage devices within the data center.
Correct answer: C
Explanation
The correct answer, C, identifies a critical business requirement for ensuring operational continuity during a datacenter failure. Option A specifies a technical performance metric but does not reflect a business need. Option B discusses budget constraints rather than a requirement, and option D focuses on resource usage instead of a fundamental business necessity.