VMware vSAN 8.x Administrator — Question 32
A customer is deploying VCF at a new datacenter location. They will migrate their workloads from the existing datacenter to the new VCF platform over six months. Both datacenters will run simultaneously for six months during the migration.
Which of the following should be a documented risk?
Answer options
- A. Six months may not be enough time to complete the migration.
- B. There will be connectivity between the two locations.
- C. Bandwidth between the two locations is sufficient to accommodate the workload migration.
- D. Workloads will be powered off during migration.
Correct answer: A
Explanation
The correct answer is A because there is a possibility that the six-month timeframe may not be adequate to complete the migration, which poses a risk to the project timeline. Options B and C are not risks; they state facts about connectivity and bandwidth, which are necessary for successful migration. Option D is incorrect as it suggests a scenario that is not aligned with the migration plan since workloads should remain operational during the migration.