Scrum Master Certified (SMC) — Question 8

During a Scrum of Scrums Meeting certain questions are answered. Which of the following are the questions answered?
A) What has my team been working on since the last meeting?
B) What will my team do until the next meeting?
C) What were other teams counting on our team to finish that remains undone?
D) What is our team planning on doing that might affect other teams?

Answer options

Correct answer: C

Explanation

The correct answer is C as it includes the relevant questions related to team dependencies and impacts on other teams. Options A and B do not fully capture the necessary questions for collaboration between teams, while D is too broad since not all inquiries are directly relevant.