Scrum Master Certified (SMC) — Question 57

Who among the following can directly approve changes recommended in the project?

Answer options

Correct answer: B

Explanation

The Scrum Guidance Body is responsible for providing oversight and guidance regarding Scrum practices, which includes the authority to approve changes. The Product Owner, Scrum Master, and Senior Management do not have the direct authority to approve changes as per the Scrum framework.