Scrum Master Certified (SMC) — Question 57
Who among the following can directly approve changes recommended in the project?
Answer options
- A. Product Owner
- B. Scrum Guidance Body
- C. Scrum Master
- D. Senior Management
Correct answer: B
Explanation
The Scrum Guidance Body is responsible for providing oversight and guidance regarding Scrum practices, which includes the authority to approve changes. The Product Owner, Scrum Master, and Senior Management do not have the direct authority to approve changes as per the Scrum framework.