Scrum Master Certified (SMC) — Question 55
You are the Scrum Master of a project to construct an IT Tech Park. This project requires adhering to stringent quality standards at every stage of development. A
Scrum Core Team is formed for this project in which the Scrum Master is supposed to facilitate a "team first" mentality when it comes to quality. You must ensure all of the following to maintain quality in Scrum, EXCEPT:
Answer options
- A. Any quality related error must be fixed only at the end to ensure that the deliverable is Done.
- B. Iterative Product development, repetitive testing, and documentation help ensure quality is inherent in each Done deliverable.
- C. Any quality requirement must consider the capacity and willingness of the organization to meet the business need.
- D. The changing needs of the customers must be incorporated during the increments.
Correct answer: B
Explanation
The correct answer is B because it emphasizes proactive quality assurance through iterative development and testing, which is essential in Scrum. Options A, C, and D are incorrect as they suggest practices that either delay quality assurance or ignore customer needs, which contradicts the principles of Scrum.