Scrum Master Certified (SMC) — Question 53
Which of the following meetings is not usually Time-boxed?
Answer options
- A. Daily Standup.
- B. Scrum of Scrums.
- C. Sprint Planning Meeting.
- D. Sprint Review.
Correct answer: B
Explanation
The Scrum of Scrums is generally not time-boxed, allowing for more flexibility in discussion among different teams. In contrast, the Daily Standup, Sprint Planning Meeting, and Sprint Review have defined time limits to ensure efficiency and focus.