Scrum Master Certified (SMC) — Question 51

To enable collaboration, the Product Owner, the Scrum Master, and the Scrum Team collaborate with each other and the stakeholders to create deliverables that provide the greatest possible value to the customer. This ensures realization of all the following project benefits, EXCEPT:

Answer options

Correct answer: A

Explanation

Option A is correct because while collaboration facilitates many aspects of project management, it does not inherently ensure efficient management of numerous Change Requests. The other options highlight valid benefits of collaboration, such as risk management, task alignment, and process improvement.