Scrum Master Certified (SMC) — Question 5
Which of the following best describes why Epics are decomposed into smaller User Stories during a Sprint?
Answer options
- A. Tasks are easier to complete.
- B. Scrum Teams are smaller in size.
- C. Too large to be completed in a Sprint.
- D. Take considerably longer time to review.
Correct answer: A
Explanation
The correct answer is A because smaller tasks are more manageable and can be completed more efficiently within the time constraints of a Sprint. Options B and C do not directly address the benefit of decomposition, while option D focuses on review time rather than completion capability.