Scrum Master Certified (SMC) — Question 49

Which of the following about User Story Acceptance Criteria is true?

Answer options

Correct answer: C

Explanation

The correct answer is C because it is indeed the responsibility of the Scrum Master to protect the integrity of the Acceptance Criteria throughout the Sprint. Option A is incorrect as Acceptance Criteria adds objectivity, not subjectivity. Option B is misleading since the Scrum Master does not decide completion; it is based on the team and the definition of done. Option D is also incorrect; while the team should be aware of changes, it's primarily the Scrum Master's role to manage Acceptance Criteria changes.