Scrum Master Certified (SMC) — Question 35
While creating the Sprint Backlog, the Scrum Team along with the Scrum Master and Product Owner must consider which of the following as inputs?
Answer options
- A. Length of Sprint, Agreed Actionable Improvements, Done Criteria, Team Calendar.
- B. Assigned Action Items, Business Improvements, Dependencies, Team Calendar.
- C. Length of Sprint, Previous Sprint Velocity, Dependencies, Team Calendar.
- D. Proof of Concept, Previous Sprint Velocity, Done Criteria, Team Calendar.
Correct answer: C
Explanation
The correct answer is C because the Length of Sprint and Previous Sprint Velocity directly influence the planning and expected workload for the upcoming Sprint. The other options include irrelevant or less critical factors that do not directly contribute to the formation of the Sprint Backlog.