Scrum Master Certified (SMC) — Question 3

Impediments are a part of any project. Which of the following is NOT true about impediments in Scrum?

Answer options

Correct answer: C

Explanation

The correct answer is C because impediments can be documented by anyone involved in the project, not just team members. Options A, B, and D correctly describe characteristics of impediments in Scrum, such as their impact on productivity and the importance of discussing them during meetings.