Scrum Master Certified (SMC) — Question 3
Impediments are a part of any project. Which of the following is NOT true about impediments in Scrum?
Answer options
- A. They reduce the productivity of a Scrum team.
- B. Impediments can be both internal and external.
- C. Impediments should be documented only by the team members in the Impediment Log.
- D. Impediments faced are brought up by the Scrum Team during the Daily Standup Meeting.
Correct answer: C
Explanation
The correct answer is C because impediments can be documented by anyone involved in the project, not just team members. Options A, B, and D correctly describe characteristics of impediments in Scrum, such as their impact on productivity and the importance of discussing them during meetings.