Scrum Master Certified (SMC) — Question 27

Which of the following events does NOT help the Scrum Team in identifying or resolving risks?

Answer options

Correct answer: D

Explanation

The Daily Standup Meeting, Sprint Planning Meeting, and Financial Planning Meeting all facilitate discussions around potential risks and how to mitigate them. However, the Prioritized Product Backlog Review Meeting primarily focuses on prioritization and refining the backlog, not specifically on risk identification or resolution.