Scrum Master Certified (SMC) — Question 25
As a Scrum Master, you have to coordinate with the Product Owner to ensure that an appropriate Length of Sprint is determined keeping in mind the changes expected. Which of the following statements is true in this regard?
Answer options
- A. It is advisable to consider the Release Dates for the overall product or service to determine the Length of Sprint.
- B. The impact and frequency of expected changes do not have any impact on the decision related to the Length of Sprint.
- C. If the project is stable, with only minor changes expected, the Length of Sprint should be relatively shorter, 1 to 3 weeks.
- D. To get maximum benefits from a Scrum project, it is always recommended to keep the Sprint Time-boxed to 6 weeks.
Correct answer: C
Explanation
Option C is correct because a stable project with minimal changes is best suited to shorter Sprints, allowing for quicker feedback and adjustments. Option A misguides by suggesting that release dates dictate Sprint length, while Option B incorrectly claims that expected changes have no relevance. Option D is also inaccurate as a fixed 6-week Sprint is not always beneficial, and flexibility in Sprint length is key to Scrum.