Scrum Master Certified (SMC) — Question 11
Listed below are some risks and issues that might be encountered during the course of a project. Identify which of the following are risks (not issues).
A) After extensive training, marketing representatives might still not be ready to take orders after the project is launched.
B) The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.
C) Funding was not approved.
D) Requirements, as currently defined, are unclear.
Answer options
- A. Only Ð’
- B. A and C
- C. Ð’ and D
- D. A and B
Correct answer: B
Explanation
Risks are potential future events that could impact the project, whereas issues are current problems. In this case, options A and C represent risks because they refer to uncertain future events (readiness of representatives and funding approval), while B and D are more about current situations or problems.