Choose the correct statements about the Failover Plan functionality: (Choose two.)

Answer options

Correct answer:

Explanation

Options A and C are correct because undo failover is applicable to the entire group, and Failover Plans need to be set up before a disaster occurs to ensure readiness. Options B and D are incorrect; while a Commit failback option exists, it does not imply that the whole group can be failed back in one action, and a Failover Plan does require finalization to be effective.