Veeam Certified Engineer (VMCE) v9 — Question 27
Which of the following options should be selected in order to temporarily bring up a production VM that has been previously been replicated to the DR site, while the production VM itself is brought down by a problem?
Answer options
- A. Failback of the Replica VM
- B. Failover Plan
- C. Planned Failover of the Replica VM
- D. Failover of the Replica VM
Correct answer: C
Explanation
The correct answer is C, as a Planned Failover of the Replica VM allows for a controlled switch to the replica while ensuring data integrity. Option A is incorrect because it refers to returning control to the production VM, not bringing up the replica. Option B is too vague, and D does not ensure that the failover is pre-planned, which is critical in a production environment.