Veeam Certified Engineer (VMCE) v12 — Question 115

A Veeam administrator with a large production infrastructure needs to justify to management why a request to purchase additional hardware resources should be granted when the resources will only be utilized off hours during backup time. The administrator decides a graphical representation will improve the likelihood that the request is approved.

Which Veeam ONE feature below provides the right details?

Answer options

Correct answer: C

Explanation

The correct answer is C. Deployment Projects provides insights and graphical representations that can help justify the need for additional resources during backup times. The other options, such as Business View and Jobs Calendar, do not focus on providing the necessary graphical details to support the resource request.