Veeam Certified Engineer (VMCE) 2021 — Question 87
A failback of three VMs has just completed, after having failed over earlier from production to the disaster recovery site. What next actions are available?
Answer options
- A. Undo failback, Commit failback
- B. Cancel failback, Commit failback
- C. Undo failback, Permanent failback
- D. Cancel failback, Permanent failback
Correct answer: A
Explanation
The correct answer is A because after a failback, you can either undo the operation if needed or commit the failback to finalize the action. Options B, C, and D are incorrect because 'Cancel failback' does not apply post-failback completion, and 'Permanent failback' is not a valid next step in this context.