LEED Green Associate (LEED GA) — Question 92
Who is the most responsible for monitoring ongoing energy performance over the life of the building?
Answer options
- A. LEED AP
- B. Contractor
- C. Facility Manager
- D. Commissioning (Cx) Agent
Correct answer: C
Explanation
The Facility Manager is primarily responsible for the ongoing monitoring of energy performance after the building is completed. While the LEED AP, Contractor, and Commissioning (Cx) Agent play important roles during the design and construction phases, it is the Facility Manager's duty to ensure that the building operates efficiently over time.