LEED Green Associate (LEED GA) — Question 86

A project has 16 employees working for four hours per day, 20 employees working six hours per day, and 10 employees working eight hours per day. What is the Full Time Equivalent (FTE) occupancy of the project?

Answer options

Correct answer: B

Explanation

The Full Time Equivalent (FTE) is calculated by converting all part-time hours into equivalent full-time hours. In this case, the total hours worked is calculated and then divided by the standard full-time hours to determine that the correct answer is 33 (B), while the other options do not accurately reflect the total FTE calculation.