UiPath Automation Developer Professional v1 — Question 119
“Process A” is scheduled to run at 2:00 PM using a time trigger with the Schedule ending of job execution feature configured to stop the job after 20 minutes. Assuming that the robots are busy and “Process A” is queued until 2:05 PM, at what time will “Process A” be stopped?
Answer options
- A. 2:20 PM
- B. 2:25 PM
- C. 2:05 PM
- D. 2:28 PM
Correct answer: B
Explanation
'Process A' starts at 2:05 PM and has a maximum execution time of 20 minutes, meaning it will finish at 2:25 PM. The other options are incorrect because 2:20 PM is before the process starts, 2:05 PM is when it begins, and 2:28 PM is after the process should have completed.