TOGAF Enterprise Architecture Practitioner — Question 93
Consider the following statements describing the TOGAF ADM.
1. All ADM activities are carried out within an iterative cycle of continuous architecture definition and realization
2. The Requirements Management phase is a continuous phase
3. Output from an early phase may be modified in a later phase
4. When a phase starts, the previous phase closes
Which statements are correct?
Answer options
- A. 2, 3 & 4
- B. 1, 2 & 3
- C. 1, 3 & 4
- D. 1, 2 & 4
Correct answer: B
Explanation
The correct answer is B because statements 1, 2, and 3 accurately reflect the principles of the TOGAF ADM, highlighting the iterative nature of the process and the continuous role of Requirements Management. Statement 4 is incorrect since a phase does not necessarily close when the next one begins; the phases can overlap.