TOGAF Enterprise Architecture Practitioner — Question 72

Consider the following statement:

Separate projects may operate their own ADM cycles concurrently, with relationships between the different projects.

What does it illustrate?

Answer options

Correct answer: D

Explanation

The statement illustrates Iteration, as it highlights the ability for different projects to run their own ADM cycles concurrently, which is a key concept in iterative development. The other options do not accurately represent this concurrent operation of projects within their ADM cycles.