TOGAF Enterprise Architecture Practitioner — Question 59

In which part of the ADM cycle do building block gaps become associated with work packages that will address the gaps?

Answer options

Correct answer: D

Explanation

The correct answer is D, as Phase E focuses on the opportunities and solutions that stem from the identified building block gaps, leading to the creation of work packages. The other phases mentioned do not specifically address the association of these gaps with actionable work packages.