TOGAF Enterprise Architecture Practitioner — Question 22
Complete the following sentence.
In the ADM, documents which are under development and have not undergone any formal review and approval process are called _________. Documents which have been reviewed and approved are called ___________.
Answer options
- A. “concept” - “deliverable”
- B. “draft” - “approved”
- C. “Version 0.1” - “Version 1.0”
- D. “draft”- “finalized”
Correct answer: B
Explanation
The correct answer is B because 'draft' describes documents that are still in progress, while 'approved' refers to those that have successfully passed the review process. Options A, C, and D do not accurately represent the stages of document development and approval in the ADM context.